OBJECTIVE

To set Workdays in a Project Schedule.

BACKGROUND

Set Workdays for your Project Schedule to avoid scheduling tasks on Non-Workdays.

STEPS TO SET WORKDAYS IN A SCHEDULE

  1. Navigate to the desired Project via the Left Sidebar
  2. Select the Calendars & Schedules tab
  3. Choose the Scheduling category
  4. Click the Toolbar icon at the top right of the Schedule Gantt Progress pane
  5. In the Tools tab, click Set Workdays
    1. This will open the Workdays and Holidays window
  6. Check the days that are considered Workdays for this Project
  7. Click Save