My task with a predecessor didn't automatically move up when its predecessor was completed early. Why?

ConstructionOnline does not automatically move a successor task when its predecessor is completed early. This is due to the fact that the following task(s) and/or resource(s) may not be available to begin earlier than originally scheduled. If you'd like to move up a Schedule Task so that it starts as soon as possible, mark the Schedule Task as ASAP using the lightning bolt ⚡ column in the List View of the Schedule!