OBJECTIVE

To show a one week Schedule view in ConstructionOnline

BACKGROUND

Do you want to highlight the tasks for the next week in your schedule? No problem. Selecting the one week schedule view will help you do just that in ConstructionOnline.

THINGS TO CONSIDER

  • You can easily return to your standard schedule view by clicking Show All Tasks

STEPS TO SHOW A ONE WEEK SCHEDULE VIEW

  1. Navigate to the desired Project via the Left Sidebar
  2. Select the Calendars & Schedules tab
  3. Highlight the Task you wish to convert to a Group
  4. Choose the Scheduling category
  5. Click the Toolbar icon at the top right of the Schedule Gantt Progress pane
  6. In the View tab, select 1 Week View