OBJECTIVE

To remove a Predecessor from a Schedule Task in ConstructionOnline.

BACKGROUND

Schedule tasks can be ordered using Predecessors. Predecessor relationships will automatically update the schedule any time a predecessor task is changed or updated. For example, if a predecessor task is delayed, any following tasks linked to that predecessor will automatically shift to later dates to reflect the delay. If for some reason you need to remove a Predecessor, you can do it a few simple steps.

STEPS TO REMOVE A PREDECESSOR FROM A SCHEDULE TASK

  1. Navigate to the desired Project via the Left Sidebar
  2. Select the Calendars & Schedules tab
  3. Choose the Scheduling category
  4. Locate the Task with the Predecessor you wish to remove
  5. Click into the Predecessor column and erase the Predecessor
    1. Changes are automatically saved