- ConstructionOnline Knowledge Base
- Scheduling
- FAQ: Scheduling
-
Getting Started
-
FAQs
-
Workflows
-
Manage Account
-
Manage Company Users
-
Contacts
-
Lead Tracking
-
Opportunities
-
Projects
-
Estimating
-
Change Orders
-
Client Selections
-
Purchasing
-
Invoicing
-
Items Database & Costbooks
-
Accounting Integrations
-
Scheduling
-
Calendars
-
To Do Lists
-
Punch Lists
-
Checklists
-
Daily Logs
-
GamePlan™
-
Time Tracking
-
Communication
-
RFIs
-
Submittals
-
Transmittals
-
Redline™ Takeoff
-
Redline™ Planroom
-
Files & Photos
-
Company Reporting
-
CO™ Drive
-
Using the ClientLink™ Portal
-
Using the TeamLink™ Portal
-
SuiteLink
-
CO™ Mobile App
-
ConstructionOnline API
How do I make my predecessor start X days before/after another task ends?
To add a delay or overlap to an existing predecessor, append a + or - sign and the number of additional days to the existing predecessor relationship. For example, let's say you want to add a 2-day delay to task 2, whose start is dependent on the completion of task 1. You would update the existing predecessor format of 1fs to be 1fs + 2, which would account for the extra 2-day delay.
More information on schedule predecessors can be found here.