Create a Baseline Report

OBJECTIVE

To create a Baseline Report in ConstructionOnline

BACKGROUND

Compare the current schedule to a Baseline to see how your schedule timeline has changed by generating a Schedule Baseline Report.

STEPS TO CREATE A BASELINE REPORT

  1. Navigate to the desired Project via the Left Sidebar
  2. Select the Calendars & Schedules tab
  3. Choose the Schedule Reports category
  4. Hover over the Baseline Report & click Create

    1. This will open the Baseline Report window
  5. Select the Baseline and enter any additional notes
  6. Click Create
    1. The Report will open in a new tab
  7. You can Share, Save, Download, Edit, or Print the Report from this tab

    HAVE MORE QUESTIONS?

    We're here to help! Chat with a Specialist by clicking the orange Chat icon in the bottom left corner or Contact UDA Support for additional options.