Set Workdays in a Schedule
OBJECTIVE
To set Workdays in a Project Schedule.
BACKGROUND
Set Workdays for your Project Schedule to avoid scheduling tasks on Non-Workdays.
STEPS TO SET WORKDAYS IN A SCHEDULE
- Navigate to the desired Project via the Left Sidebar
- Select the Calendars & Schedules tab
- Choose the Scheduling category
- Click the Toolbar icon at the top right of the Schedule Gantt Progress pane

- In the Tools tab, click Set Workdays
- This will open the Workdays and Holidays window
- Check the days that are considered Workdays for this Project
- Click Save