Remove a Predecessor from a Schedule Task
OBJECTIVE
To remove a Predecessor from a Schedule Task in ConstructionOnline.
BACKGROUND
Schedule tasks can be ordered using Predecessors. Predecessor relationships will automatically update the schedule any time a predecessor task is changed or updated. For example, if a predecessor task is delayed, any following tasks linked to that predecessor will automatically shift to later dates to reflect the delay. If for some reason you need to remove a Predecessor, you can do it a few simple steps.
STEPS TO REMOVE A PREDECESSOR FROM A SCHEDULE TASK
- Navigate to the desired Project via the Left Sidebar
- Select the Calendars & Schedules tab
- Choose the Scheduling category
- Locate the Task with the Predecessor you wish to remove
- Click into the Predecessor column and erase the Predecessor
- Changes are automatically saved
HAVE MORE QUESTIONS?
- Frequently asked questions (FAQ) regarding OnPlan Scheduling can be found in the FAQ: Scheduling article.
- If you need additional assistance, chat with a Specialist by clicking the orange Chat icon located in the bottom left corner or visit the UDA support page for additional options.