How do I set predecessors in a schedule?
Predecessors can be set by navigating to the Predecessor column within the List View of your Schedule and entering the predecessor's Task Number. ConstructionOnline automatically applies the Finish - Start ("fs") predecessor relationship to each task by default, but three other predecessor relationships are available within ConstructionOnline's OnPlan Scheduling:
- Finish - Finish (#ff)
- Start - Finish (#sf)
- Start - Start (#ss)
For more details on how predecessors function in ConstructionOnline™, visit the Understanding Predecessors article.