Set a Schedule Task to ASAP

OBJECTIVE

To set a Schedule Task to ASAP in ConstructionOnline

BACKGROUND

Schedule tasks can be ordered using Predecessors. Predecessor relationships will automatically update the schedule any time a predecessor task is changed or updated. For example, if a predecessor task is delayed, any following tasks linked to that predecessor will automatically shift to later dates to reflect the delay.

THINGS TO CONSIDER

  • Setting a Schedule Task to ASAP will result in it starting as soon as its predecessor relationship will allow it to.

STEPS TO SET A SCHEDULE TASK TO ASAP

  1. Navigate to the desired Project via the Left Sidebar
  2. Select the Calendars & Schedules tab
  3. Choose the Scheduling category
  4. Double-click on the Schedule Task you wish to edit
    1. This will open the Task Details window
  5. Check the ASAP box
  6. Click Save